The two project management essentials: identifying dependencies and the critical path

Every delayed launch I have witnessed had the same root cause: someone missed a dependency or started an activity too late, not realizing it was on the critical path. While there are many important skills and tools in project management that all matter, two skills dwarf all others in deciding if a project leader is successful: identifying dependencies and determining the critical path. It’s not obvious, but if you can’t map dependencies and determine the critical path the project will likely fail. 

Today, I want to explain why exactly I believe that you can’t be successful without these two underappreciated skills. Before I do that, I want to shortly make the case for project management in today’s world. 


The Backlog is a newsletter about the undervalued and overlooked in modern product development. It covers product development, self organization, and productivity. I include methods, books, and write about my own experience. The target audience are Product Managers or Product Owners, Scrum Masters, Developers, and project leaders. The Backlog is about getting the most out of product development.
Subscribe to get new posts straight to your inbox. 


Project management’s role today

Some claim project management is no longer relevant. They say things have changed too much. The rate of change is extreme. Uncertainty is soaring. They conclude that projects are pointless in this environment. Instead, iteratively improving the product is the key. 

All of that is true. 

But I do not think any of this is at odds with using projects to organize work. Most of us are still building products in the confines of an organization with launch windows, market events, regulatory deadlines, or simply the need to align multiple departments or teams. Projects can be of great help there. 

A project is, in essence, a defined outcome to achieve by a certain date with a limited amount of money spent. That’s also product development, except that it doesn’t stop after achieving an outcome. You simply move on to the next one.  

The way projects are defined and executed has changed. Product development used to be far less complex. It was easier to foresee exactly what needed to be done at what point in time. Thus, it was reasonable to create a detailed plan at the onset clearly defining the outputs that were to be produced and the necessary steps to get there.

Today, teams start with a goal, an outcome they want to achieve by a certain time. However, the team doesn’t necessarily know how exactly it will get there. It also doesn’t know what outputs it will produce to achieve the outcome. Things are not as set in stone at the onset of a project as they used to be. And project leaders need to be more flexible in adapting the scope of the project. 

But there is a goal, a timeframe, and a budget. There is a project. This is useful. Project management has a place in today’s environment.

The two keys to being successful in project management

I don’t want to diminish all that is necessary to be successful as a project leader. Communication and conflict resolution, decision making, stakeholder management, and leadership are important. Having a firm grasp of the tools like project charters, roadmaps, or risk assessments matters. So much more is important. 

However, I believe none of that will help you if you are not able to identify dependencies and determine the critical path.

Identifying dependencies

Project management often seems to chiefly consist of two things. Making sure what needs to get done actually gets done. And making sure everyone has what they need to be able to execute. In this context it is crucial to understand how activities, products, and teams depend on each other. 

Being able to identify dependencies means being able to foresee the impacts of actions or decisions on others. It means being able to take preventative measures, even if that is simply informing someone about some minor change. This enables smooth execution and reduces wait times, double work, bad quality, or other forms of waste that always result in project delay.  

To illustrate, we once changed the interface between products (in our case a digital API, but what follows is also true in a physical interface). We made sure everyone was prepared but forgot a team that used the interface for a non-obvious use case and broke their integration. This caused a roll-back, rework, and frustrated customers. This happens more often than you think, often to Business Intelligence teams that are forgotten consumers of an API. 

I was also once part of a team that didn’t have all necessary skills. Handling this usually means support from some other team. We didn’t identify it upfront and weren’t able to warn the other team. This team wasn’t able to plan for our request for supporting us. We had to ask for help on short notice and had to wait, ending up delayed and frustrated. 

The examples mentioned may seem obvious when written here. But they are not. Projects are delayed all over organizations every day of the week. The ability to identify non-obvious dependencies is the skill necessary to avoid these delays. 

Determining the critical path

The critical path consists of the longest stretch of dependent activities from beginning to the end of the project. In other words, it is the sequence of activities that cannot be fully parallelized. The summed-up duration of all activities on the critical path is the shortest the project will be.

Identifying the critical path is really a follow-up of identifying the dependencies between activities and thus determining which activities are truly important to achieve a deadline. Most are not. And if they are not on the critical path, they are not urgent. Unfortunately, many project leaders don’t understand this and treat every activity the same. They manufacture urgency for non-critical work and lack energy or time for the actual critical path because they never identified it. 

I liken it to Marty Cagan’s high-integrity commitments. Similarly to a product manager only committing to truly important deadlines and then pushing to achieve those, project leaders should only apply pressure to those activities/teams/people that are on the critical path. 

They need to be able to identify those first. Without this, the project will not only be delayed, the project leader will likely burn out following up and pressuring every small activity to be completed as soon as possible. 

Practical tips on identifying dependencies and the critical path

Most experienced project leaders seem to develop a sixth sense. They have a feeling of what the truly important activities are and are able to highlight the seemingly unimportant connections between activities, teams, and products. 

In identifying dependencies between activities and consequently the critical path, I haven’t found a better solution than the classic roadmap. I am not its biggest fan. But visualizing the high-level activities that are necessary and their connections is to me still the best way to identify the critical path. The key here is to build it by talking to every team that may be involved in the project and understand their contribution. In all of these discussions, I conclude by asking who else I should talk to to understand what needs to be done. This sounds simple, but it is an effective method to gather all task dependencies. 

There are techniques like network diagrams and PERT you can use to calculate the critical path and the float of the activities. But this, to me, is overkill and suggests an unrealistic amount of certainty about the future.

Besides identifying dependencies between activities, the roadmap automatically visualizes dependencies between teams working on activities. It also makes activities apparent where the product team is missing skills. 

To identify product dependencies, I tend to conduct a small workshop with engineers from various teams with the goal of visualizing how product components are connected. This also sounds simple, but it works. There are also tools you can use to automatically create a dependency graph between services or products.

Overall, project leaders must be curious and ask questions in order to create a deep understanding of all aspects of the project. This will help uncover dependencies. 

Conclusion

Identifying dependencies and determining the critical path are essential for project leaders. These skills are a superpower. They allow you to foresee what will likely happen, almost like being able to tell the future. 

Having these skills won’t solve all your problems but they will mean smoother execution and less delay. Most importantly, identifying dependencies and the critical path will allow you to focus on what is truly important and not burn out by chasing the trivial.